Adds $156,397.94 to Redgwick's Claremont Middle School turf field contract
This change order adds $156,397.94 to the district's contract with Redgwick Construction, raising the limit from $635,957.95 to $792,355.89. The added work is demolition and installation of a new turf at Claremont Middle School.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Redgwick Construction · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $156,397.94
- Previous total
- $635,957.95
- New total
- $792,355.89
- Schools
- Claremont Middle School
- Funding
- Fund 21, Measure J
- Resource / site
9450/9711-210- Vendor no.
003557- Presented by
- Deputy Chief, Facilities Planning and Management
- File
19-1538· agendaP.-15- Outcome
- Adopted on the General Consent Report, Aug 14, 2019
Official text
Approval by the Board of Education of Change Order No. 1, Contract for Construction Services between District and Redgwick Construction, Oakland, CA, for the latter to provide demolition and installation of a new turf, in conjunction with the Claremont Middle School Playfield Project, in the additional amount of $156,397.94, increasing the Contract not to exceed amount from $635,957.95 to $792,355.89. All other terms and conditions of the Contract remain in full force and effect
History
- Adopted on the General Consent Report