No bid
$63K

Awards Johnson Controls $62,957, with no competitive bid, for sprinkler monitoring work at district sites

Johnson Controls Fire Protection will install the current sprinkler inspector's test valve and install and relocate sprinkler riser monitoring devices as part of a district-wide fire alarm project. The contract is for $62,957, with work from October 11, 2019 to April 12, 2020, or within 180 days of the notice to proceed. The district did not put this contract out to competitive bid.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
New agreement
Category
School buildings & construction
Term
Oct 11, 2019 – Apr 12, 2020
This vote
$62,957
Funding
Fund 21 Measure B
Resource / site
9399-918
Vendor no.
004981
Presented by
Deputy Chief, Facilities Planning and Management
File
19-1779 · agenda P.-12
Outcome
Adopted on the General Consent Report, Oct 10, 2019

Official text

Approval by the Board of Education of Resolution No. 1920-0025 - Award of Agreement Between Owner and Contractor for the Various For Alarm District Wide Project - Non Competitively Bid - to Johnson Controls Fire Protection, LP, Livermore, CA, which consists of installation services for the current Sprinkler Inspector’s Test Valve, installation and relocation of Sprinkler Riser Monitoring Device, in the amount of $62,957.00, as the selected contractor, with work scheduled to commence on October 11, 2019, and scheduled to last until April 12, 2020, or with performance to be completed within 180 calendar days from date of issuance of District’s Notice to Proceed, and authorizing the President and Secretary of the Board to sign the Agreement for same with said contractor.

History

  1. Adopted on the General Consent Report

Also on the agenda: Oct 10, 2019

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.

Get Updates

Your info is safe with us.