Awards Ninyo & Moore $3,000 for extra soil review on the Piedmont kitchen project
The board is awarding Ninyo & Moore additional geotechnical (soil and ground) consulting for the Piedmont Finishing Kitchen project. The work includes checking the effect of the 2016 California Building Code and reviewing plans. The $3,000.00 includes a $1,000.00 contingency, and work runs from November 14, 2019 to December 31, 2020.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Ninyo & Moore · Oakland, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Nov 14, 2019 – Dec 31, 2020
- This vote
- $3,000
- Schools
- Piedmont
- Funding
- Fund 21, Measure J
- Resource / site
9650-146- Vendor no.
003087- Presented by
- Deputy Chief, Facilities Planning and Management
- File
19-2170· agendaP.-11- Outcome
- Adopted on the General Consent Report, Nov 13, 2019
Official text
Approval by the Board of Education of Resolution No. 1920-0040 - Award of Agreement for Engineering Services to Ninyo & Moore, Oakland, CA, for the latter to provide additional geotechnical consulting services - “Evaluate impact of 2016 California Building Code on project geotechnical report. Prepare letter to document conclusions from evaluation. Review plans, specifications, and structural calculations for conformance with the geotechnical report.” - for the Piedmont Finishing Kitchen Project, in the amount of $3,000.00, which includes a contingency fee of $1,000.00, as the selected consultant, and authorizing the President and Secretary of the Board to sign the Agreement for same with said consultant, with work scheduled to commence on November 14, 2019, and scheduled to last until December 31, 2020, pursuant to the Agreement.