Adds $376,016 for Ninyo & Moore's inspections on the Fremont construction project
The district is adding $376,016 (including a $50,000 contingency) to its agreement with Ninyo & Moore for special inspections and project management on the Fremont New Construction Project. The contract limit rises from $436,484 to $812,500, and the end date moves to February 28, 2021.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Ninyo & Moore · Oakland, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Feb 28, 2018 – Feb 28, 2021
- This vote
- $376,016
- Previous total
- $436,484
- New total
- $812,500
- Funding
- Fund 21, Measure J
- Resource / site
9650-302- Vendor no.
003087- Presented by
- Deputy Chief, Facilities Planning and Management
- File
20-0696· agendaP1.-4- Outcome
- Adopted on the General Consent Report, May 13, 2020
Official text
Approval by the Board of Education of Amendment No.3, Independent Consultant Agreement between the District and Ninyo & Moore, Oakland CA, for the latter to provide special inspections and changes to Increments 3 and 4, which includes project management, client liaison work scheduling, quality review, and semi-monthly distribution of test data and daily field inspection reports, for the Fremont New Construction Project, in an additional amount of $376,016.00, which includes a $50,000.00 contingency, increasing Agreement not to exceed amount from $436,484.00 to $812,500.00, extending the term of the Agreement from February 28, 2018 through December 31, 2020 to February 28, 2021, and authorizing the President and Secretary of the Board to sign the Amendment for same with said Consultant. All other terms and conditions of the Agreement remain in full force and effect.