Adds $40,750 and time to Verde Design's Emerson softball field contract, now up to $307,110
The board amends the agreement with Verde Design for the Emerson Elementary School Soft Ball Field Project. The added $40,750.00, which includes a $15,000.00 contingency (a cushion for unexpected costs), covers reimbursable fees to the state architect's office (DSA), and raises the cap from $266,360.00 to $307,110.00. The end date moves from December 31, 2020 to June 21, 2021.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Verde Design · Santa Clara, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jun 7, 2018 – Jun 21, 2021
- This vote
- $40,750
- Previous total
- $266,360
- New total
- $307,110
- Schools
- Emerson Elementary School
- Funding
- Fund 21 Measure J
- Resource / site
9350 115- Vendor no.
004498- Presented by
- Deputy Chief, Facilities Planning and Management
- File
20-1409· agendaP1.-4- Outcome
- Adopted on the General Consent Report, Aug 12, 2020
Official text
Approval by the Board of Education of Amendment No. 5, Independent Consultant Agreement for Professional Services between the District and Verde Design, Santa Clara, CA, for the former to provide to latter reimbursable Department of State Architect (DSA) fees, described in Exhibit A, attached to this Amendment, for the Emerson Elementary School Soft Ball Field Project, in an additional amount of $40,750.00, which includes a $15,000.00 contingency, increasing Agreement not to exceed amount from $266,360.00 to $307,110.00, extending term of Agreement from June 7, 2018 through December 31, 2020 to June 21, 2021 and authorizing the President and Secretary of the Board to sign the Amendment for same with said Consultant.
History
- Adopted on the General Consent Report