Adds $9,417.05 and 120 days to One Workplace's Glenview furniture contract
One Workplace is supplying new furniture for the Glenview New Construction Project. This amendment adds $9,417.05, raising the agreement limit from $607,405.23 to $616,822.28, and extends the term by 120 days to April 30, 2021.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Notes on the official text
- The added amount is printed as "$9,417.05.00", a punctuation misprint, but the stated totals ($607,405.23 to $616,822.28) confirm the intended amount of $9,417.05.
- Vendor / partner
- One Workplace · San Leandro, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Mar 12, 2020 – Apr 30, 2021
- This vote
- $9,417.05
- Previous total
- $607,405.23
- New total
- $616,822.28
- Funding
- Fund 21 Measure J
- Resource / site
9650 119- Vendor no.
003183- Presented by
- Deputy Chief, Facilities Planning and Management
- File
20-2426· agendaV1.-2- Outcome
- Adopted on the General Consent Report, Jan 13, 2021
Official text
Approval by the Board of Education of Amendment No. 1, General Services Agreement between the District and One Workplace, San Leandro, CA, for the latter to provide delivery and purchase of new furniture for the Glenview New Construction Project, in an additional amount of $9,417.05.00 increasing Agreement not to exceed amount from $607,405.23 to $616,822.28, extending time of Agreement by 120 additional calendar days, revising term from March 12, 2020 through December 31, 2020 to April 30, 2021, authorizing the President and Secretary of the Board to sign the Amendment for same with said Consultant. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report