Voted on separatelyAfter work beganRaises existing contractText discrepancyMulti-year
+$2.47Mnew total $49.7M

Adds $2.47M to Overaa/Tulum's construction contract for the Foster The Center central kitchen

This is the third change order to the district's lease-leaseback construction agreement with Overaa/Tulum for the new central kitchen at the Foster The Center project. It adds $2,465,319.59, raising the contract's not-to-exceed amount from $47,187,998.25 to $49,653,317.84, and extends the completion deadline to February 17, 2021. Approval depends on Change Orders No. 1 and 2 also being approved.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Discrepancy from the official text. The text extends the completion deadline from February 20, 2018 to February 17, 2021 but calls this an additional 361 calendar days, which does not match the span between those dates. (Confirmed by a second, independent AI reading.)

Pulled from the consent vote. Adopted in its own vote at this meeting (7–0), instead of with the rest of the consent report.

· Adopted (passed). A motion was made by President Gonzales, seconded by Director Yee,that this Agreement or Contract be Adopted. The motion carried by the following vote.

  • Jessica Ramos P Aye
  • Samantha Pal Absent
  • Aimee Eng Aye
  • VanCedric Williams Aye
  • Gary Yee Aye
  • Mike Hutchinson Aye
  • Clifford Thompson Aye
  • Benjamin "Sam" Davis Aye
  • Shanthi Gonzales Aye
Action
Change order
Category
School buildings & construction
Term
Feb 17, 2021
This vote
$2,465,319.59
Previous total
$47,187,998.25
New total
$49,653,317.84
Funding
Fund 21 Measure J
Resource / site
9799 184
Vendor no.
003224
Presented by
Deputy Chief, Facilities Planning and Management
File
21-0334 · agenda V1.-5
Outcome
Adopted, Mar 10, 2021

Official text

Approval by the Board of Education of Change Order No. 3, Lease-Leaseback Agreement (LLA) for the Foster The Center Project with Overaa/Tulum (“Contractor”), Richmond, CA, for the latter to provide the construction services delineated in said Charge Order for the Center New Central Kitchen, in the amount of $2,465,319.59, increasing the LLA not to exceed amount from $47,187,998.25 to $49,653,317.84, extending the current completion deadline of February 20, 2018 to February 17, 2021, an additional 361 calendar days. Approval of Change Order No. 3, LLA between the District and Overaa/Tulum/Eclipse is conditioned upon the concurrent approval of Change Orders No. 1 (21-0481) and 2 (21-0482). All other terms and conditions of the LLA remain in full force and effect.

History

  1. Adopted

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.