Adds $2.47M to Overaa/Tulum's construction contract for the Foster The Center central kitchen
This is the third change order to the district's lease-leaseback construction agreement with Overaa/Tulum for the new central kitchen at the Foster The Center project. It adds $2,465,319.59, raising the contract's not-to-exceed amount from $47,187,998.25 to $49,653,317.84, and extends the completion deadline to February 17, 2021. Approval depends on Change Orders No. 1 and 2 also being approved.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Pulled from the consent vote. Adopted in its own vote at this meeting (7–0), instead of with the rest of the consent report.
· Adopted (passed). A motion was made by President Gonzales, seconded by Director Yee,that this Agreement or Contract be Adopted. The motion carried by the following vote.
- Jessica Ramos P Aye
- Samantha Pal Absent
- Aimee Eng Aye
- VanCedric Williams Aye
- Gary Yee Aye
- Mike Hutchinson Aye
- Clifford Thompson Aye
- Benjamin "Sam" Davis Aye
- Shanthi Gonzales Aye
- Vendor / partner
- Overaa/Tulum · Richmond, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Feb 17, 2021
- This vote
- $2,465,319.59
- Previous total
- $47,187,998.25
- New total
- $49,653,317.84
- Funding
- Fund 21 Measure J
- Resource / site
9799 184- Vendor no.
003224- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-0334· agendaV1.-5- Outcome
- Adopted, Mar 10, 2021
Official text
Approval by the Board of Education of Change Order No. 3, Lease-Leaseback Agreement (LLA) for the Foster The Center Project with Overaa/Tulum (“Contractor”), Richmond, CA, for the latter to provide the construction services delineated in said Charge Order for the Center New Central Kitchen, in the amount of $2,465,319.59, increasing the LLA not to exceed amount from $47,187,998.25 to $49,653,317.84, extending the current completion deadline of February 20, 2018 to February 17, 2021, an additional 361 calendar days. Approval of Change Order No. 3, LLA between the District and Overaa/Tulum/Eclipse is conditioned upon the concurrent approval of Change Orders No. 1 (21-0481) and 2 (21-0482). All other terms and conditions of the LLA remain in full force and effect.
History
- Adopted