Adds $985,871.35 to Overaa/Tulum's Foster The Center kitchen contract for schedule delay costs

This is the first change order to the district's lease-leaseback construction agreement with Overaa/Tulum for the new central kitchen at the Foster The Center project. It adds $985,871.35 for extended general conditions caused by delays tied to fire alarm scope, Health Department scope and PG&E. It raises the not-to-exceed amount from $44,844,035.00 to $45,829,906.35 and moves the deadline from August 8, 2019 to January 31, 2020.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Discrepancy from the official text. The text extends the completion deadline from August 8, 2019 to January 31, 2020 and calls it an additional 149 calendar days, but those dates are 176 days apart. (Confirmed by a second, independent AI reading.)

Pulled from the consent vote. Adopted in its own vote at this meeting (7–0), instead of with the rest of the consent report.

· Adopted (passed). A motion was made by Director Yee, seconded by President Gonzales,that this Agreement or Contract be Adopted. The motion carried by the following vote.

  • Jessica Ramos P Aye
  • Samantha Pal Absent
  • Aimee Eng Aye
  • VanCedric Williams Aye
  • Gary Yee Aye
  • Mike Hutchinson Aye
  • Clifford Thompson Aye
  • Benjamin "Sam" Davis Aye
  • Shanthi Gonzales Aye
Action
Change order
Category
School buildings & construction
Term
Jan 31, 2020
This vote
$985,871.35
Previous total
$44,844,035
New total
$45,829,906.35
Funding
Fund 21 Measure J
Resource / site
9569 184
Vendor no.
003224
Presented by
Deputy Chief, Facilities Planning and Management
File
21-0481 · agenda V1.-6
Outcome
Adopted, Mar 10, 2021

Official text

Approval by the Board of Education of Change Order No. 1, Lease-Leaseback Agreement (LLA) Between the District and Overaa/Tulum/Eclipse, Richmond, CA, for the latter to provide construction services which consist of extended general conditions due to schedule delays caused by Fire Alarm scope, Health Department scope, and PG&E delays for the New Central Kitchen for the Foster The Center Project, in the amount of $985,871.35, increasing the Contract not to exceed amount from $44,844,035.00 to $45,829,906.35, extending the current completion deadline of August 8, 2019 to January 31, 2020 (an additional 149 calendar days), as selected Contractor, pursuant to the Change Order. All other terms and conditions of the LLA remain in full force and effect.

History

  1. Adopted

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.