Adds $1.36M to Overaa/Tulum's Foster The Center kitchen contract for equipment, fencing and security
This is the second change order to the district's lease-leaseback construction agreement with Overaa/Tulum for the new central kitchen at the Foster The Center project. It adds $1,358,091.90 for preliminary change orders covering extra equipment and fencing requested by Nutritional Services, extended site security, and fixes for conflicts in the construction drawings. It raises the not-to-exceed amount from $45,829,906.35 to $47,187,998.25 and extends the deadline 22 days, to February 22, 2020.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Overaa/Tulum/Eclipse · Richmond, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Feb 22, 2020
- This vote
- $1,358,091.90
- Previous total
- $45,829,906.35
- New total
- $47,187,998.25
- Funding
- Fund 21 Measure J
- Resource / site
9569 184- Vendor no.
003224- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-0482· agendaV1.-7- Outcome
- Adopted on the General Consent Report, Mar 10, 2021
Official text
Approval by the Board of Education of Change Order No. 2, Lease-Leaseback Agreement (LLA) Between the District and Overaa/Tulum/Eclipse, Richmond, CA, for the latter to provide construction services which includes Various PCOs for additional equipment and fencing as requested by Nutritional Service and extended site security due to schedule extension, scope to address conflicts in the CDs for the New Central Kitchen for the Foster The Center Project, in the amount of $1,358,091.90, increasing the Contract not to exceed amount from $45,829,906.35 to $47,187,998.25, extending the current completion deadline of January 31, 2020 to February 22, 2020 (an additional 22 calendar days), as selected Contractor, pursuant the Change Order. Approval of Change Order No. 2, LLA between the District and Overaa/Tulum/Eclipse is conditioned upon the concurrent approval of Change Order No. 1 (21-0481). All other terms and conditions of the LLA remain in full force and effect.
History
- Adopted on the General Consent Report