Cuts $17,273.51 from the Mar Con Builder contract for the Laurel Finishing Kitchen project
This change order settles unused allowance money with Mar Con Builder for the Laurel Finishing Kitchen Project. It lowers the contract price by $17,273.51, from $2,732,000.00 to $2,714,726.49. The completion date stays July 25, 2019.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Mar Con Builder, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jul 25, 2019
- This vote
- $17,273.51
- Previous total
- $2,732,000
- New total
- $2,714,726.49
- Funding
- Fund 21, Measure J
- Resource / site
9450-131- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-0815· agendaV1.-2- Outcome
- Adopted on the General Consent Report, Apr 28, 2021
Official text
Approval by the Board of Education of Change Order No. 1, Agreement between the District and Mar Con Builder, Inc., Oakland, CA, for reconciliation with the latter of unused allowance for the Laurel Finishing Kitchen Project, as a deductive change in the amount of $17,273.51, reducing the Agreement price from $2,732,000.00 to $2,714,726.49, (completion date remains July 25, 2019). All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report