After work beganMulti-year
−$23Knew total $1.22M

Cuts $22,546 from Mar Con Builders' Elmhurst Middle boiler job and extends it to September 2020

This change order closes out the Elmhurst Middle School Boiler Replacement Project with Mar Con Builders and returns unused contingency money. It lowers the contract price by $22,546.00, from $1,238,116.00 to $1,215,570.00. It also extends the end date from July 30, 2019 to September 30, 2020.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
Change order
Category
School buildings & construction
Term
Apr 25, 2019 – Sep 30, 2020
This vote
$22,546
Previous total
$1,238,116
New total
$1,215,570
Schools
Elmhurst Middle School
Funding
Fund 21, Measure J
Resource / site
9350-229
Vendor no.
002712
Presented by
Deputy Chief, Facilities Planning and Management
File
21-0831 · agenda V1.-5
Outcome
Adopted on the General Consent Report, Apr 28, 2021

Official text

Approval by the Board of Education of Change Order No. 1, Agreement between the District and Mar Con Builders, Inc., Oakland, CA, for Project completion and reconciling, with the latter, the remaining contingency for the Elmhurst Middle School Boiler Replacement Project, in the amount of $22,546.00, reducing the Agreement price from $1,238,116.00 to $1,215,570.00, and extending the term from April 25, 2019 thru July 30, 2019 to September 30, 2020.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.