Pays Consolidated Engineering Labs up to $36,367 for testing and inspection on Lincoln Elementary repairs
Consolidated Engineering Laboratories will provide materials testing and construction inspection for the Lincoln Elementary School water intrusion repairs. The basic services cost $26,367, and the district adds $10,000 for extra services if needed. Work began June 16, 2021, before this approval, and is scheduled to last until August 23, 2021, though it may run later if delays occur.
Plain-English summary written by AI from the official text. Reviewed Oct 4, 2026
- Vendor / partner
- Consolidated Engineering Laboratories · Oakland, CA
- Action
- New agreement
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jun 16, 2021 – Aug 23, 2021
- This vote
- $36,367
- Schools
- Lincoln Elementary School
- Funding
- Fund 35 County School Facilities Fund
- Resource / site
7710-133- Vendor no.
001171- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-1623· agendaV.-6- Outcome
- Adopted on the General Consent Report, Aug 11, 2021
Official text
Approval by the Board of Education of Agreement for Materials Testing Services by and between the District and Consolidated Engineering Laboratories, Oakland, CA, for the latter to provide materials testing and construction inspection services for the Lincoln Elementary School Water Intrusion Repairs Project, in the amount of $26,367.00 for basic services, with the District adding a 10% contingency fee of $10,000 for additional services, if needed, for a total not to exceed amount of $36,367.00, with work scheduled to commence on June 16, 2021, and scheduled to last until August 23, 2021, but may not be completed until later if delays in design or construction arise.
History
- Adopted on the General Consent Report