Adds $12,122.87 to Mar Con Builders' Global Family playground matting contract
This change order adds $12,122.87 for an extra utility site scan, asphalt for the new playground location, and capping and filling a drain at the previous playground location at Global Family Elementary School. It raises the contract from $88,320.00 to $100,442.87 and extends the term by 212 days to May 31, 2021. The contract term began September 16, 2020, before this approval.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Mar Con Builders · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Sep 16, 2020 – May 31, 2021
- This vote
- $12,122.87
- Previous total
- $88,320
- New total
- $100,442.87
- Schools
- Global Family Elementary School
- Funding
- Fund 21, Measure J
- Resource / site
9650-114- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-1908· agendaV1.-3- Outcome
- Adopted on the General Consent Report, Sep 22, 2021
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Oakland, CA, for the additional utility site scan for new playground location, installation of asphalt, cover the existing drain with metal grade plug and fill with asphalt on previous playground location, for the Global Family Elementary School Playmatting Installation Project, in the amount of $12,122.87, increasing the Agreement price from $88,320.00 to $100,442.87 and extending the Agreement term by 212 days, from September 16, 2020 through October 31, 2020 to May 31, 2021.
History
- Adopted on the General Consent Report