Pays N.V. Heathorn Company $16,346 for steam pipe and tank repairs at The Center at Foster
The district hires N.V. Heathorn Company to remove a stainless-steel chemical pipe from the steam header and cap it, then reconnect piping to the feed water tank with a new check valve and repaired insulation, as described in the company's July 12, 2021 proposal. The amount is $16,346.00, for work from September 23, 2021 to December 31, 2021.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- N.V. Heathorn Company · Concord, CA
- Action
- New agreement
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Sep 23, 2021 – Dec 31, 2021
- This vote
- $16,346
- Schools
- The Center at Foster
- Funding
- Fund 21 Measure J
- Resource / site
9350-184- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-1985· agendaV1.-4- Outcome
- Adopted on the General Consent Report, Sep 22, 2021
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and N.V. Heathorn Company, Concord, CA, for the latter to provide the latter to remove the stainless-steel chemical pipe to the steam header, install caps, remove insulation on the feed water tank to expose nipple, drain tank, route stainless steel pipe on ( E ) hangers to feed water tank, install new check valve and repair insulation, with services including all work described in the July 12, 2021, proposal attached to this Agreement as Exhibit A, for the Center at Foster Project, in the amount of $16,346.00, with work scheduled to commence on September 23, 2021, and scheduled to last until December 31, 2021.
History
- Adopted on the General Consent Report