Cuts $1,492 from Piedmont Avenue Elementary playmatting contract with Mar Con Builders
This change order returns an unused allowance, lowering Mar Con Builders' contract price from $192,000 to $190,508. It also extends the contract end date to September 12, 2021. The original contract was competitively bid.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Mar Con Builders · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Sep 11, 2020 – Sep 12, 2021
- This vote
- $1,492
- Previous total
- $192,000
- New total
- $190,508
- Schools
- Piedmont Avenue Elementary School
- Funding
- Fund 21, Measure J
- Resource / site
9650-16- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
21-2089· agendaV1.-1- Outcome
- Adopted on the General Consent Report, Oct 13, 2021
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor - District and Mar Con Builders, Oakland, CA, for reconciliation of unused allowance for the Piedmont Elementary School Playmatting Installation Project, as a deductive change in the amount of $1,492.00, reducing the contract price from $192,000.00 to $190,508.00, and an adjustment to Contract Time In This Change Order: 271 Calendar Days, extending the term from September 11, 2020 through December 15, 2020 to September 12, 2021. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report