Raises existing contractLarge increase
+$816new total $2K

Adds $816 for Syserco's work on the Elmhurst Middle School boiler replacement

This amendment adds four hours of work for Syserco, Inc. on the boiler replacement at Elmhurst Middle School. It raises the contract limit from $891 to $1,707.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
Amendment
Category
School buildings & construction
This vote
$816
Previous total
$891
New total
$1,707
Schools
Elmhurst Middle School
Funding
Fund 21 Measure J
Resource / site
9350 229
Vendor no.
004166
Presented by
Deputy Chief, Facilities Planning and Management
File
21-2190 · agenda V1.-3
Outcome
Adopted on the General Consent Report, Oct 13, 2021

Official text

Approval by the Board of Education of Amendment No. 1, Agreement Between Owner and Contractor, by and between the District and Syserco, Inc., Oakland CA, for the latter to provide an additional four hours to complete the work or services, for the Elmhurst Middle School Boiler Replacement Project, as described in the Proposal, dated August 31, 2021, attached to this Amendment as Exhibit A. in an additional amount of $816.00, increasing Agreement not-to-exceed amount from $891.00 to $1,707.00. All other terms and conditions of the Agreement remain in full force and effect.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.