Awards ER Plumbing $50,000 to replace the sewer main at Montera Middle School gym
ER Plumbing & Construction will replace about 200 feet of 6-inch sewer pipe from the gym building at Montera Middle School. The $50,000 includes up to $6,500 held in reserve for additional costs. ER Plumbing was the lowest responsible bidder, and work is expected from March 24 to June 21, 2022.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- ER Plumbing & Construction · Oakland, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Mar 24, 2022 – Jun 21, 2022
- This vote
- $50,000
- Schools
- Montera Middle School
- Funding
- Fund 140. Deferred Maintenance
- Resource / site
9914 211- Vendor no.
001567- Presented by
- Deputy Chief, Facilities Planning and Management
- File
22-0508· agendaV.-5- Outcome
- Adopted on the General Consent Report, Mar 23, 2022
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and ER Plumbing & Construction, Oakland, CA, for the latter to replace 6” sewer pipe from the gym to the main hole, approximately 200’ of pipe and connections work under the contract for the Montera Middle School Sewer Mainline Gym Building Contract Project, in the amount of $50,000.00, which includes a not-to-exceed general contingency allowance of $6,500.00, to pay any additional amounts to which the Contractor may be entitled under the Contract Documents other than special allowances, as the lowest responsible, responsive bidder, with the work anticipated to commence on March 24, 2022, and scheduled to last for ninety (90) days, with an anticipated ending of June 21, 2022.
History
- Adopted on the General Consent Report