Adds $16,980 and 181 days for N.V. Heathorn's extra repairs at The Center at Foster
This change order adds extra construction work at The Center at Foster project: repairing a cart wash duct and ceiling, a leaking steam valve and pipes, and a broken heat recovery pipe, plus removing old equipment from the roof. It raises the contract price from $16,346 to $33,326 and extends the end date by 181 days, to June 30, 2022.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- N.V. Heathorn Company · Concord, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Sep 23, 2021 – Jun 30, 2022
- This vote
- $16,980
- Previous total
- $16,346
- New total
- $33,326
- Schools
- The Center at Foster
- Funding
- Fund 21 Building Fund, Measure B
- Resource / site
9799 184- Vendor no.
007292- Presented by
- Board of Education
- File
22-0596· agendaV1.-1- Outcome
- Adopted on the General Consent Report, May 25, 2022
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor of Change Order No. 1 by and between the District and N.V. Heathorn Company, Concord, CA, for the latter to provide additional construction services, which consist of repairing a cart wash duct & ceiling, repairing a leaking steam valve and pipes, replace and remove duroblocks, remove old VFDs from the roof, and fix a broken heat recovery pipe connected to refrigeration equipment, for The Center at Foster Project, in the amount of $16,980.00, increasing the contract price from $16,346.00 to $33,326.00 and extending the term of Agreement from September 23, 2021 through December 31, 2021, by 181 days, to June 30, 2022.