Adds $35,137.04 to G & G Builders' contract for paving work at Burckhalter Elementary
This change order adds construction work caused by unforeseen conditions at Burckhalter Elementary School: demolishing asphalt, laying new asphalt paving and installing a concrete rat slab. It raises the contract's not-to-exceed amount from $59,813.00 to $94,950.04. All other terms stay the same.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- G & G Builders, Inc. · Livermore, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $35,137.04
- Previous total
- $59,813
- New total
- $94,950.04
- Schools
- Burckhalter Elementary School
- Funding
- Fund 21 Building Fund, Measure J
- Resource / site
9650-105- Vendor no.
001772- Presented by
- Deputy Chief, Facilities Planning and Management
- File
22-2269· agendaT.-5- Outcome
- Adopted on the General Consent Report, Oct 26, 2022
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and G & G Builders, Inc., Livermore, CA, for the latter, due to unforeseen conditions, to provide additional construction services which includes demolition of asphalt, new asphalt paving and concrete rat slab installation, for the Burckhalter Elementary School Site Improvements Project, in the additional amount of $35,137.04, increasing the not to exceed amount of the Agreement from $59,813.00 to $94,950.04. All other terms and conditions of the Agreement remain in full force and effect.