Adds $227,030 to Ninyo & Moore's contract for added environmental cleanup work at Fremont High
The district is expanding an existing environmental services contract with Ninyo & Moore for the Fremont High School new construction project. The added work revises a cleanup plan and prepares completion and monitoring reports requested by the California Department of Toxic Substances Control. The change adds $206,391.00 for basic services plus $20,639.10 for additional services, $227,030.10 in all, raising the contract limit from $175,645.80 to $402,675.90.
Plain-English summary written by AI from the official text. Reviewed Oct 3, 2026
Corrected Oct 3, 2026: The amount added by this action was corrected from $206,391 (basic services only) to $227,030.10 (basic plus additional services).
- Vendor / partner
- Ninyo & Moore · Alameda, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $227,030.10
- Previous total
- $175,645.80
- New total
- $402,675.90
- Funding
- Fund 21 Building Fund, Measure J
- Resource / site
9650-302- Vendor no.
003087- Presented by
- Deputy Chief, Facilities Planning and Management
- File
22-2666· agendaT.-6- Outcome
- Adopted on the General Consent Report, Dec 14, 2022
Official text
Approval by the Board of Education of Amendment No. 1, General Services Agreement by and between the District and Ninyo & Moore, Alameda, CA, for the latter to provide the following amended services: To provide additional environmental services which include revising the draft Remedial Action Workplan (RAW) into a modified RAW that will include the Remedial Action Completion Report (RACA) based on the requests of the California Department of Toxic Substances Control (DTSC) and prepare monitoring Operation and Maintenance (O&M) Reports, as described in the Proposal dated October 6, 2022, attached to this Amendment, as part of Exhibit A, for the Fremont High School New Construction Project, in an additional amount of $206,391.00 for Basic Services and $20,639.10 for Additional Services, increasing the Agreement not-to-exceed amount from $175,645.80 to $402,675.90. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report