Awards Pinguelo Construction $3.05M to replace windows at Havenscourt and Lockwood campuses
The district is hiring Pinguelo Construction, Inc. of Fairfield to remove old windows and install new dual-pane windows at three buildings on the Havenscourt Middle School and Lockwood STEAM Academy campuses. The lump sum of $3,045,000 includes $60,000 in contingency allowances, and Pinguelo was the lowest responsive, responsible bidder. Work is expected to run from January 26, 2023 to January 25, 2024.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Pinguelo Construction, Inc. · Fairfield, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jan 26, 2023 – Jan 25, 2024
- This vote
- $3,045,000
- Schools
- Havenscourt Middle School, Lockwood STEAM Academy
- Funding
- Fund 140 Deferred Maintenance
- Resource / site
9914-232- Vendor no.
008194- Presented by
- Deputy Chief, Facilities Planning and Management
- File
22-2882· agendaT.-1- Outcome
- Adopted on the General Consent Report, Jan 25, 2023
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and Pinguelo Construction, Inc., Fairfield, CA, for the latter to provide construction services which consist of Demolish existing windows, patching, and painting of openings inside and out as needed. F&I [Furnish and Install] new three sectional windows, top section stationary, two lower sections operable, awning type, with four- inch opening restrictors (1st floor only), dual pane low E rating tinted glass, window guards, rest room panes to be obscure, dark bronze finish frames. Shop drawings are required for approval. Havenscourt Middle School Campus Building M (Coliseum Academy Prep) - 95 windows - approximately 3' x7' high, bidders to verify. Lockwood Campus Building E - 48 windows - approximately 3' x7' high, bidders to verify. The Lockwood Kindergarten Building B - 91 windows of different sizes -This building has a variation of different type and size windows on all nine sides of the building. The classroom windows will have awning type with four-inch opening restrictors in the middle of the frame and fixed windows top and bottom, for the Havenscourt Middle School Campus Building M (Coliseum Academy Prep) and Lockwood Building E to match existing windows on the Havenscourt Middle School Campus Building M (Coliseum Academy Prep) 66th Avenue Street elevation, for the Havenscourt Middle School Building M (Coliseum College Prep) and Lockwood STEAM Academy Window Replacement Project, in the lump sum amount of $3,045,000.00, which includes contingency allowances totaling $60,000.00, as the lowest responsive, responsible bidder, with the work anticipated to commence on January 26, 2023, and scheduled to last for three hundred sixty-five days (365), with an anticipated ending of January 25, 2024.
History
- Adopted on the General Consent Report