Adds $59,460 and a year to Noll & Tam's design work for the Urban Promise Academy portable move
This amendment adds assessment and design work for relocating portable classrooms at the Urban Promise Academy campus, including a site visit and drawings of existing conditions. The added amount includes a $5,400 contingency (a cushion for unexpected costs). It raises the contract limit from $31,988 to $91,448 and extends the end date to December 31, 2024.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Pulled from the consent vote. Adopted in its own vote at this meeting (7–0), instead of with the rest of the consent report.
· Adopted (passed). A motion was made by Director Benjamin "Sam" Davis, seconded by Vice President Thompson, that this Agreement or Contract be Adopted. The motion carried by the following vote:.
- Linh Le Absent
- Natalie Gallegos Chavez Absent
- Benjamin "Sam" Davis Aye
- Jennifer Brouhard Aye
- VanCedric Williams Aye
- Nick Resnick Aye
- Valarie Bachelor Aye
- Clifford Thompson Aye
- Mike Hutchinson Aye
- Vendor / partner
- Noll & Tam Architects · Berkeley, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Dec 15, 2022 – Dec 31, 2024
- This vote
- $59,460
- Previous total
- $31,988
- New total
- $91,448
- Schools
- Urban Promise Academy
- Funding
- Fund 35 County School Facilities Fund
- Resource / site
7710 236- Vendor no.
008175- Presented by
- Deputy Chief, Facilities Planning and Management
- File
22-2932· agendaT.-2- Outcome
- Adopted, Feb 8, 2023
Official text
Approval by the Board of Education of Amendment No. 1, Agreement for Architectural Services by and between the District and Noll & Tam Architects, Berkeley, CA, for the latter to provide assessment and design services which consist of reviewing existing documentation, creating drawings backgrounds, conducting a site visit to document existing conditions, meet with district representatives to discuss existing conditions, as described in the Proposal dated November 1, 2022, attached to this Amendment as Exhibit A, in an additional amount of $59,460.00, which includes a not-to-exceed contingency of $5,400.00, increasing Agreement’s not-to-exceed amount from $31,988.00 to $91,448.00, and extending the term of the Agreement from December 15, 2022 through December 31, 2023 to December 31, 2024, (an additional 366 days). All other terms and conditions of the Agreement remaining in full force and effect.
History
- Adopted