Adds $49,147.06 to CWS Construction's Castlemont High field and bleachers contract for repairs
This change order adds drainage, sewer and concrete repairs to the Castlemont High School field and bleachers replacement project. The work comes from several preliminary change orders (PCOs), including new base rock, plumbing fixes for restroom floor drains, and traffic-rated lids for turf field drain boxes. It raises the contract limit from $8,619,585.71 to $8,668,732.77.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- CWS Construction Group, Inc. · Novato, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $49,147.06
- Previous total
- $8,619,585.71
- New total
- $8,668,732.77
- Schools
- Castlemont High School
- Funding
- Fund 21 Building Fund, Measure Y
- Resource / site
9655-301- Vendor no.
007886- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-0167· agendaT.-3- Outcome
- Adopted on the General Consent Report, Feb 22, 2023
Official text
Approval by the Board of Education of Change Order No. 2, Agreement Between Owner and Contractor by and between the District and CWS Construction Group, Inc., Novato, CA, for additional construction services which consists of PCO #8 - Install of new aggregate base rock in shot put area. PCO #11 - Concrete blocking main sewer line of south restroom, removed portion with concrete and replaced. PCO# 12 -Removal of existing floor drains in existing restrooms (4) and install trap primers at each floor drain. PCO #13 -Repair/patch existing concrete floor to complete installation of trap primers. PCO II 14 - Traffic rated lids (4) for drain boxes on turf field, as well as one replacement drain box which completely collapsed, for the Castlemont High School Field and Bleachers Replacement Project, in the amount of $49,147.06, increasing the not to exceed amount of the Agreement from $8,619,585.71 to $8,668,732.77. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report