Adds $46,783 for Applied Materials & Engineering's extra testing at Castlemont High's field project
The district is adding $46,783 to its contract with Applied Materials & Engineering, Inc. of Oakland for extra inspection and testing at the Castlemont High School field and bleachers project. The added work covers unanticipated concrete placements, anchor rod testing, concrete block (CMU) coring and review of submitted documents. The contract's total limit rises from $53,938.50 to $100,721.50, and the end date moves to May 31, 2023, which is 92 more days.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Applied Materials & Engineering, Inc. · Oakland, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Apr 28, 2022 – May 31, 2023
- This vote
- $46,783
- Previous total
- $53,938.50
- New total
- $100,721.50
- Schools
- Castlemont High School
- Funding
- Fund 21, Building Funds, Measure J
- Resource / site
9650 301- Vendor no.
000468- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-0181· agendaU.-8- Outcome
- Adopted on the General Consent Report, Feb 22, 2023
Official text
Approval by the Board of Education of Amendment No. 1, Materials Testing and Special Inspection Services Agreement by and between the District and Applied Materials & Engineering, Inc., Oakland, CA, for the latter to provide additional special inspection and testing services, which includes multiple unanticipated concrete placements, anchor rod testing CMU coring & submittal review for the Castlemont High School Field & Bleachers Project, as described in proposal dated January 10, 2023, attached as Exhibit A, incorporated herein by reference as though fully set forth, in an additional amount of $46,783.00, which includes a not-to-exceed contingency of $4,253.00, for Additional Services, increasing Agreement’s total not-to-exceed amount from $53,938.50 to $100,721.50, and extending the term of the Agreement from April 28, 2022 through February 28, 2023 to May 31, 2023, (an additional 92 days). All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report