Approves up to $200,000 for a battery storage system at Castlemont High through 2034
SolarStorage Fund D, LLC of Richmond will install and maintain a battery storage system for the Castlemont High School Energy Efficiency and Safety Project. The ten-year agreement runs March 9, 2023 through October 2, 2034 at a cost not to exceed $200,000, with up to five one-year extensions at fair market value. The Board also authorizes a filing that the project is exempt from review under the California Environmental Quality Act.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- SolarStorage Fund D, LLC · Richmond, CA
- Action
- New agreement
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Mar 9, 2023 – Oct 2, 2034
- This vote
- $200,000
- Schools
- Castlemont High School
- Funding
- Fund 21 Building Fund, Measure Y
- Resource / site
9655-301- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-0102· agendaU.-1- Outcome
- Adopted on the General Consent Report, Mar 8, 2023
Official text
Approval by the Board of Education of Resolution Number 2223-0174 - Castlemont High School Battery Service Energy Efficiency and Safety [Approval of Battery Services Agreement By and Between SolarStorage Fund D, LLC, Richmond, CA, and District, for installation and maintenance of Battery Storage System, for the Castlemont High School Energy Efficiency and Safety Project, for a term of ten years, March 9, 2023 through October 2, 2034, at a cost not to exceed $200,000.00, with up to five (5) one-year periods at fair market value extension of Agreement term; and authorization for Superintendent of Schools or designee to file a categorical exemption relating under CEQA to the project.]
History
- Adopted on the General Consent Report