After work beganText discrepancyMulti-year
$13Knot to exceed

Pays King Construction Inspection up to $13,046 to inspect solar work at Lowell and Westlake

King Construction Inspection will act as the inspector of record for the solar equipment replacement project at Lowell Middle School and Westlake Middle School, as required by the Division of the State Architect (DSA). The limit of $13,046 includes up to $1,186 for additional services. The text lists the work as starting April 27, 2022 and lasting until September 30, 2023.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Discrepancy from the official text. The text says work commences April 27, 2022 and lasts until September 30, 2023, so the start date is a year before this April 2023 meeting and the contract term is unclear. (Confirmed by a second, independent AI reading.)
Action
New agreement
Category
School buildings & construction
Term
Apr 27, 2022 – Sep 30, 2023
This vote
$13,046
Schools
Lowell Middle School, Westlake Middle School
Funding
Fund 21 Building Funds Measure J
Resource / site
9650 918
Vendor no.
007828
Presented by
Deputy Chief, Facilities Planning and Management
File
23-0933 · agenda U.-6
Outcome
Adopted on the General Consent Report, Apr 26, 2023

Official text

Approval by the Board of Education Agreement for Inspector of Record Services for Construction by and between the District and King Construction Inspection, Inc., Berkeley, CA, for the latter to provide construction project inspection services, as required by the Division of the State Architect (DSA) for Application No. 01-12079, for the Lowell Middle School and Westlake Middle School Solar Initiative Inverter Replacement Project, in the not to-exceed amount of $13,046.00, which includes a not-to-exceed contingency fee of $1,186.00 for additional services, with work scheduled to commence on April 27, 2022, and scheduled to last until September 30, 2023.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.