Awards Andy's Roofing $258,145 to replace the cafeteria roof at Skyline High School
Andy's Roofing Company, Inc. of San Leandro will strip the existing roof down to the deck, install a new roof, and repair and match damaged cement plaster at the Skyline High School cafeteria. The amount includes a contingency, and the company was the lowest responsive, responsible bidder. Work starts May 25, 2023 and lasts 60 days, ending around July 23, 2023.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Andy's Roofing Company, Inc. · San Leandro, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- May 25, 2023 – Jul 23, 2023
- This vote
- $258,145
- Schools
- Skyline High School
- Funding
- Fund 140 Deferred Maintenance
- Resource / site
9914 306- Vendor no.
008462- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-1178· agendaT.-21- Outcome
- Adopted on the General Consent Report, May 24, 2023
Official text
Approval by the Board of Education of an Agreement Between Owner and Contractor by and between the District and Andy’s Roofing Company, Inc., San Leandro, CA, for the latter to provide removal and installation of new roof which consist of removing the existing roofing system down to the underlying roof deck; installation of a new flute in-fill at structural roof deck, removal of spaIled sections of cement plaster, plaster to match existing in texture and finish for the Skyline High School Cafeteria Roof Replacement Project, in the amount of $258,145.00, which includes a contingency of $33,000.00, as the lowest responsive, responsible bidder, with the work anticipated to commence on May 25, 2023, and scheduled to last for sixty days (60), with an anticipated ending of July 23, 2023.