Adds $8,756.89 to Native Soil's Allendale Elementary site improvements contract
This change order pays Native Soil, Inc. for extra work at the Allendale Elementary School Site Improvements Project, including more soil removal for in-ground planters, irrigation valves and wiring, and drip lines for trees. It also gives a discount for six planters in place of 10 planter boxes. The contract limit rises from $55,989.81 to $64,746.70.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Native Soil, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $8,756.89
- Previous total
- $55,989.81
- New total
- $64,746.70
- Schools
- Allendale Elementary School
- Funding
- Fund 01 General Fund
- Resource / site
0006-101- Vendor no.
007827- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-1728· agendaT.-18- Outcome
- Adopted on the General Consent Report, Sep 13, 2023
Official text
Approval by the Board of Education of Change Order No. 1, Construction Agreement Between Owner and Contractor by and between the District and Native Soil, Inc., Oakland, CA, for the latter to provide additional soil removal for in ground planters including equipment rental and off haul fees, discount to six planners in lieu of 10 planter boxes, valves for veggie planters with irrigation boxes, fittings and run new wires to the controller and laterals for the new planters, drip line and bubblers for the trees for the Allendale Elementary School Site Improvements Project, in the additional amount of $8,756.89, increasing the Agreement not to exceed amount from $55,989.81 to $64,746.70. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report