Awards G & G Builders $190,928 for new play matting and equipment at Laurel Elementary
G & G Builders, Inc. will buy and install play matting tiles, remove an existing play structure, and install tetherball poles and basketball hoops at Laurel Elementary School. The amount includes a $26,000 contingency, and the company was the lowest responsive bidder. Work is expected to start October 26, 2023 and finish by November 24, 2023.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- G & G Builders, Inc. · Livermore, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Oct 26, 2023 – Nov 24, 2023
- This vote
- $190,928
- Schools
- Laurel Elementary School
- Funding
- Fund 1/S&C Carryover
- Resource / site
0006/918- Vendor no.
001772- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-2161· agendaT.-2- Outcome
- Adopted on the General Consent Report, Oct 25, 2023
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and G & G Builders, Inc., Livermore, CA, for the latter to procure the play matting tiles and coordinate the play matting tiles delivery on site, provide installation of tiles, demolition to existing play structure, matting, tetherball poles, and basketball hoops for the Laurel Elementary School Site Improvements Project, in the amount of $190,928.00, which includes a contingency of $26,000.00, as the lowest responsive bidder, with the work anticipated to commence on October 26, 2023, and required to be completed within ninety days (90), with an anticipated ending of November 24, 2023.