Adds $7,150 and extends HERTZ Environmental's stormwater closeout at Claremont to June 2024
This amendment adds $7,150 to HERTZ Environmental's contract to close out the Storm Water Pollution Prevention Plan for the Claremont Middle School Multipurpose Room and Kitchen Project. The contract limit rises from $23,500 to $30,650. The end date moves from December 31, 2023 to June 28, 2024, an additional 180 days.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- HERTZ Environmental, Inc. · San Francisco, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Mar 24, 2022 – Jun 28, 2024
- This vote
- $7,150
- Previous total
- $23,500
- New total
- $30,650
- Schools
- Claremont Middle School
- Funding
- Fund 21/Measure Y
- Resource / site
9655/201- Vendor no.
002056- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-2789· agendaU.-4- Outcome
- Adopted on the General Consent Report, Jan 24, 2024
Official text
Approval by the Board of Education of Amendment No. 2, General Services Agreement by and between the District and HERTZ Environmental, Inc., San Francisco, CA, extending the term of Agreement from March 24, 2022 through December 31, 2023 to June 28, 2024, an additional 180 calendar days, for the latter to continue to provide closeout of the Storm Water Pollution Prevention Plan for the Claremont Middle School Multipurpose Room and Kitchen Project, in the additional amount of $7,150.00, increasing the not to exceed amount of the Agreement from $23,500.00 to $30,650.00. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report