Adds $39,658 to MarCon Builders' Community Day campus contract for fire alarm and electrical work
A change order adds $39,658 to MarCon Builders' contract for the Community Day Campus Building Modification Project, raising the cap from $287,771 to $327,429. The added work is fire alarm and electrical panel relocation and testing, covered by preliminary change orders (PCOs) 1, 7, 8 and 14. The Board also declares that public bidding would be futile for this added work, so it is not being bid separately.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- MarCon Builders, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $39,658
- Previous total
- $287,771
- New total
- $327,429
- Schools
- Community Day School
- Funding
- Fund 21/measure Y
- Resource / site
9655/333- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
23-2856· agendaU.-1- Outcome
- Adopted on the General Consent Report, Feb 14, 2024
Official text
Approval by the Board of Education of Resolution No 2324-0166 - Declaring the Futility of Public Bidding for the Additional Fire Alarm and Electrical Panel Relocation and Testing Work at Community Day School and Approving A Change Order [No. 2] for That Work [By and Between the District and MarCon Builders, Inc., Oakland, CA - PCO 1;7; 8; 14, attached, for the Community Day Campus Building Modification Project, in the additional amount of $39,658.00, increasing the Agreement not to exceed amount from $287,771.00 to $327,429.00. All other terms and conditions of the Agreement remain in full force and effect.]
History
- Adopted on the General Consent Report