Adds $156,911 to Kaiser Child Development Center site work with Mar Con Builders and extends it to June 2024
The contractor will do four added items on the Kaiser Child Development Center Site Improvements Project: three new play structures, a concrete curb between pavers and asphalt, expansion joints at a retaining wall, and removal of a concrete apron that does not meet Americans with Disabilities Act rules. The change order raises the contract limit from $6,551,440.00 to $6,708,351.00 and adds 239 calendar days, so work now ends June 30, 2024.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Mar Con Builders, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jun 8, 2023 – Jun 30, 2024
- This vote
- $156,911
- Previous total
- $6,551,440
- New total
- $6,708,351
- Schools
- Kaiser Child Development Center
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9655 812- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-0475· agendaU.-1- Outcome
- Adopted on the General Consent Report, Apr 10, 2024
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, for the latter to perform: · PCO #12 for installation of 3 new play structures. · PCO #13 for 6" wide 24" deep concrete curb placed as a divider between pavers and existing asphalt. · PCO #14 for expansion joints needed at retaining wall. · PCO #15 for demolition of concrete apron that is not ADA compliant for the Kaiser Child Development Center Site Improvements Project, in the additional amount of $156,911.00, increasing the not to exceed amount of the Agreement from $6,551,440.00 to $6,708,351.00; and extending the term of the Agreement by an additional 239 Calendar Days, from June 8, 2023 through November 4, 2023 to June 30, 2024. All other terms and conditions of the Agreement remain in full force and effect.