Adds $79,567 for play mats and a track at Kaiser Child Development Center in a contract with Mar Con Builders
This change order adds soft play-mat tiles, a solar-reflecting track on the lower yard near the portables, and extra planting to the Kaiser Child Development Center site improvements. It covers two preliminary change orders (PCOs), numbers 27 and 28. The contract with Mar Con Builders goes up by $79,567, from $6,708,351 to $6,781,918 as stated in the text.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Notes on the official text
- The official text's numbers don't add up: $6,708,351 plus $79,567 is $6,787,918, but it states a new total of $6,781,918. The difference ($6,000) is small.
- Vendor / partner
- Mar Con Builders, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $79,567
- Previous total
- $6,708,351
- New total
- $6,781,918
- Schools
- Kaiser Child Development Center
- Funding
- Building Fund 21 Measure Y
- Resource / site
9655/812- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-1373· agendaU.-1- Outcome
- Adopted on the General Consent Report, Jun 12, 2024
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor of Change Order No. 2 by and between the District and Mar Con Builders, Inc., Oakland, CA, which includes PCO's 27 and 28, to furnish and install soft surface playmat tiles and install a solar reflecting track on the lower yard area near portables; as well supplemental planting for the Kaiser Child Development Center Site Improvements Project, in the amount of $79,567.00 increasing the contract price from $6,708,351.00 to $6,781,918.00 pursuant to the Change Order.
History
- Adopted on the General Consent Report