Adds $167,465 for 18 more window replacements at Havenscourt Middle and Lockwood STEAM Academy
This change order adds 18 window replacements for classrooms 110, 111 and 206 to the contract with Pinguelo Construction, Inc. It raises the contract limit from $3,045,000 to $3,212,465. It includes a preliminary change order (PCO 1) for the added window work.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Pinguelo Construction, Inc. · Fairfield, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $167,465
- Previous total
- $3,045,000
- New total
- $3,212,465
- Schools
- Havenscourt Middle School, Lockwood STEAM Academy
- Funding
- Fund 140 Deferred Maintenance
- Resource / site
9914 232- Vendor no.
008194- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-1732· agendaT.-13- Outcome
- Adopted on the General Consent Report, Aug 14, 2024
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Pinguelo Construction Inc., Fairfield, CA, for an additional 18 window replacements for classrooms 110, 111, and 206 which includes PCO 1 Construction of replacing windows for the Havenscourt Middle School Campus Building M (CCPA) and Lockwood STEAM Academy Window Replacement Project, in the additional amount of $167,465.00, increasing the not to exceed amount of the Agreement from $3,045,000.00 to $3,212,465.00.
History
- Adopted on the General Consent Report