$19Knot to exceed

Approves up to $18,722 for Consolidated Engineering Laboratories to test materials at Oakland Tech asphalt project

Consolidated Engineering Laboratories will provide materials testing and special construction inspection, plus a time and cost estimate, for the asphalt project at Oakland Technical High School. Work is scheduled from August 29 to October 31, 2024.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
New agreement
Category
School buildings & construction
Term
Aug 29, 2024 – Oct 31, 2024
This vote
$18,722
Schools
Oakland Technical High School
Funding
Fund 140 Deferred Maintenance
Resource / site
9914/305
Vendor no.
001171
Presented by
Deputy Chief, Facilities Planning and Management
File
24-1670 · agenda T.-4
Outcome
Adopted on the General Consent Report, Aug 28, 2024

Official text

Approval by the Board of Education of an Agreement for Materials Testing and Special Inspection Services by and between the District and Consolidated Engineering Laboratories, San Ramon CA, for the latter to provide material testing and special construction inspection services and a time and cost estimate for the Oakland Technical High School Asphalt Project in a not-to-exceed amount of $18,722.00, with work scheduled to commence on August 29, 2024, and scheduled to last until October 31, 2024.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.

Get Updates

Your info is safe with us.