Adds $110,363.01 to RK Roofing's Roosevelt Middle School gym contract for new drains
This change order pays RK Roofing & Construction for materials and installation of 20 cast iron drains, two access hatches and new plywood and waterproofing around the drains at the Roosevelt Middle School gym replacement project. It raises the contract's not-to-exceed amount from $558,795.00 to $669,158.01. All other terms of the agreement stay the same.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- RK Roofing & Construction, Inc. · San Leandro, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $110,363.01
- Previous total
- $558,795
- New total
- $669,158.01
- Schools
- Roosevelt Middle School
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9655 212- Vendor no.
009084- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-2414· agendaM.-6- Outcome
- Adopted on the General Consent Report, Oct 23, 2024
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and RK Roofing & Construction, Inc., San Leandro, CA, for the latter to provide materials and installation of 20 cast iron drains, two access hatches for drains, and new plywood and waterproofing around 20 drains, for the Roosevelt Middle School Gym Replacement Project, in the amount of $110,363.01, increasing the Agreement not-to-exceed amount from $558,795.00 to $669,158.01. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report