Adds $46,475 for Jensen Hughes fire and intrusion alarm drawing work at Melrose Leadership Academy
The district adds $46,475 to its engineering agreement with Jensen Hughes, Inc. for extra fire and intrusion alarm drawing consulting that falls outside the original scope. The limit rises from $159,570 to $206,045. The project covers fire alarm and fire sprinkler systems at Melrose Leadership Academy.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Jensen Hughes, Inc. · Concord, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $46,475
- Previous total
- $159,570
- New total
- $206,045
- Schools
- Melrose Leadership Academy
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9655 235- Vendor no.
002281- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-2526· agendaM.-7- Outcome
- Adopted on the General Consent Report, Nov 13, 2024
Official text
Approval by the Board of Education of Amendment No. 4, Agreement for Engineering Services by and between the District and Jensen Hughes, Inc., Concord, CA, for the latter to provide additional fire and intrusion alarm drawing consulting services that are outside the original scope for the District’s fire alarm and intrusion alarm systems, as described in the proposal dated July 30, 2024, attached to this Amendment as part of Exhibit A, for the Melrose Leadership Academy Fire Alarm & Fire Sprinkler Systems Engineering Services Project, in the additional amount of $46,475.00, increasing the Agreement’s not-to-exceed amount from $159,570.00 to $206,045.00. All other terms and condition of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report