Hires Cahill Contractors for up to $100,000 of preconstruction work at Melrose Leadership Academy
This lease-leaseback contract (a construction contract in which the builder leases the site to the district and the district leases it back) pays Cahill Contractors LLC to provide preconstruction services for the new classroom building and modernization at the Melrose Leadership Academy at Maxwell Park Campus. The estimated cost is not to exceed $100,000.00. Work is scheduled from October 24, 2024 to December 31, 2025, and the Facilities Committee recommended it.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Cahill Contractors LLC · Oakland, CA
- Action
- New agreement
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Oct 24, 2024 – Dec 31, 2025
- This vote
- $100,000
- Schools
- Melrose Leadership Academy at Maxwell Park Campus
- Funding
- Fund 21 Building Measure Y
- Resource / site
9655/235- Vendor no.
009054- Presented by
- Board of Education
- File
24-2408· agendaM.-1- Outcome
- Adopted on the General Consent Report, Dec 11, 2024
Official text
Approval by the Board of Education, upon the recommendation of its Facilities Committee, of a Lease-Leaseback Contract by and between the District and Cahill Contractors LLC, Oakland, CA, for the latter to provide preconstruction services for the Melrose Leadership Academy at Maxwell Park Campus New Classroom Building and Modernization Project, with work scheduled to commence on October 24, 2024, and anticipated to last until December 31, 2025, at an estimated cost not to exceed $100,000.00.
History
- Recommended Favorably (Facilities Committee)
- Adopted on the General Consent Report
- Official record on Legistar
- 24-2408 Presentation - Lease-Leaseback Contract – Cahill Contractors LLC– Melrose Leadership Academy at Maxwell Park Campus New Classroom Building and Modernization Project– Division of Facilities Planning and Management
- 24-2408 Lease-Leaseback Contract – Cahill Contractors LLC– Melrose Leadership Academy at Maxwell Park Campus New Classroom Building and Modernization Project– Division of Facilities Planning and Management