Credits back $92,338 on Mar Con's Oakland International High alarm contract
The Board approves a change order that reduces Mar Con Builders' price for the Oakland International High School intrusion alarm replacement by $92,338.00, from $920,409.00 to $828,071.00. The credit returns the contractor's remaining contingency and the cost of an unused alternate item for a new raceway. It is paid from the Measure B building fund.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Mar Con Builders, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $92,338
- Previous total
- $920,409
- New total
- $828,071
- Schools
- Oakland International High School
- Funding
- Fund 21 Building Fund Measure B
- Resource / site
9399 353- Vendor no.
002712- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-2966· agendaM.-6- Outcome
- Adopted on the General Consent Report, Jan 8, 2025
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Mar Con Builders, Inc., Oakland, CA, for the latter’s deductive Change Order charging back its remaining contingency and the amount for unused ALT (New raceway from portable to the building C & D), for the Oakland International High School Intrusion Alarm Replacement Project, in the deductive amount of $92,338.00, decreasing the Agreement price from $920,409.00 to $828,071.00. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report