Adds $91,885 and seven months to DSK Architects' West Oakland Middle School window design
This amendment adds $91,885, which includes a $7,990 contingency, for DSK Architects to provide more design services for the West Oakland Middle School Window Replacement Project. The limit rises from $598,000 to $689,885, and the end date moves from December 31, 2024 to July 31, 2025.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- DSK Architects · San Francisco, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Dec 1, 2022 – Jul 31, 2025
- This vote
- $91,885
- Previous total
- $598,000
- New total
- $689,885
- Schools
- West Oakland Middle School
- Funding
- Fund 21 Building Funds Measure Y
- Resource / site
9655 204- Vendor no.
001432- Presented by
- Deputy Chief, Facilities Planning and Management
- File
24-3145· agendaM.-6- Outcome
- Adopted on the General Consent Report, Jan 22, 2025
Official text
Approval by the Board of Education of Amendment No. 1, Agreement for Architectural Services by and between the District and DSK Architects, San Francisco, CA, for the latter to provide additional architectural and engineering design services for the West Oakland Middle School Window Replacement Project, in an additional amount of $91,885.00 (which includes a Seven Thousand Nine Hundred Ninety Dollars ($7,990.00 contingency fee), increasing the not-to-exceed amount of the Agreement from $598,000.00 to $689,885.00, and extending the term of Agreement by 212 additional calendar days, from December 1, 2022 through December 31, 2024 to July 31, 2025. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report