After work beganRaises existing contractMulti-year
+$92Knew total $690K

Adds $91,885 and seven months to DSK Architects' West Oakland Middle School window design

This amendment adds $91,885, which includes a $7,990 contingency, for DSK Architects to provide more design services for the West Oakland Middle School Window Replacement Project. The limit rises from $598,000 to $689,885, and the end date moves from December 31, 2024 to July 31, 2025.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
Amendment
Category
School buildings & construction
Term
Dec 1, 2022 – Jul 31, 2025
This vote
$91,885
Previous total
$598,000
New total
$689,885
Schools
West Oakland Middle School
Funding
Fund 21 Building Funds Measure Y
Resource / site
9655 204
Vendor no.
001432
Presented by
Deputy Chief, Facilities Planning and Management
File
24-3145 · agenda M.-6
Outcome
Adopted on the General Consent Report, Jan 22, 2025

Official text

Approval by the Board of Education of Amendment No. 1, Agreement for Architectural Services by and between the District and DSK Architects, San Francisco, CA, for the latter to provide additional architectural and engineering design services for the West Oakland Middle School Window Replacement Project, in an additional amount of $91,885.00 (which includes a Seven Thousand Nine Hundred Ninety Dollars ($7,990.00 contingency fee), increasing the not-to-exceed amount of the Agreement from $598,000.00 to $689,885.00, and extending the term of Agreement by 212 additional calendar days, from December 1, 2022 through December 31, 2024 to July 31, 2025. All other terms and conditions of the Agreement remain in full force and effect.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.