Adds $1,713.71 to Johnson Controls' contract for smoke detectors at Coliseum College Prep interim housing
This change order adds work to the district's existing maintenance contract with Johnson Controls Fire Protection. The company will replace two heat detectors with smoke detectors and add two more smoke detectors to cover four bean pockets at the Coliseum College Prep Academy interim housing. The added cost is $1,713.71, and work runs from February 27 to June 30, 2025.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Johnson Controls Fire Protection, LP · Livermore, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Feb 27, 2025 – Jun 30, 2025
- This vote
- $1,713.71
- Schools
- Coliseum College Prep Academy
- Funding
- Building Fund 21 Measure Y
- Resource / site
9655/232- Vendor no.
004981- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-0126· agendaM.-2- Outcome
- Adopted on the General Consent Report, Feb 26, 2025
Official text
Approval by the Board of Education of Change Order No. 1 to Agreement by and between the District and Johnson Controls Fire Protection, LP, Livermore, CA, for the latter to replace two existing heat detectors for smoke detectors and add two (2) more smoke detectors to cover the four (4) bean pockets for the Coliseum College Prep Academy Interim Housing in total amount of $1,713.71, with work scheduled to commence on February 27, 2025 and scheduled to last until June 30, 2025, pursuant to the Agreement.
History
- Adopted on the General Consent Report