Adds $15,128 for a concrete curb and access ramp at Manzanita Elementary's play area
This change order adds $15,128 to the contract with KM 106 Construction, Inc., raising the price from $489,513 to $504,641. The work is a concrete curb, access ramp and utility access box next to the play structure at Manzanita Elementary School, done at the owner's direction. It includes a preliminary change order (PCO) attached to the item.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- KM 106 Construction, Inc. · San Francisco, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $15,128
- Previous total
- $489,513
- New total
- $504,641
- Schools
- Manzanita Elementary School
- Funding
- Fund 01 General Fund
- Resource / site
0007 175- Vendor no.
008444- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-0467· agendaL.-3- Outcome
- Adopted on the General Consent Report, Mar 26, 2025
Official text
Approval by the Board of Education of Change Order No. 2, Agreement Between Owner and Contractor by and between the District and KM 106 Construction, Inc., San Francisco, CA, for installation of a concrete curb, concrete access ramp and utility access box adjacent to the play structure area per owner direction, which includes PCO 6 attached to this change order for the Manzanita Elementary School Site Improvement Project, in the amount of $15,128.00, increasing the contract price from $489,513.00 to $504,641.00. All other terms and conditions of the Agreement remain in full force and effect.