Hires RK Roofing for $297,000 Highland Child Development Center roof replacement
RK Roofing will tear off and replace the existing roof and roof systems at the Highland Child Development Center. The price includes a $40,000 contingency allowance, and the company was the lowest responsive, responsible bidder. Work is expected to start June 6, 2025 and finish within 60 days, by August 5, 2025.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- RK Roofing & Construction, Inc. · San Leandro, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Jun 6, 2025 – Aug 5, 2025
- This vote
- $297,000
- Schools
- Highland Child Development Center
- Funding
- OCI Oakland Children's Initiative
- Resource / site
9186 815- Vendor no.
009084- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-1020· agendaL.-14- Outcome
- Adopted on the General Consent Report, May 14, 2025
Official text
Approval by the Board of Education of an Agreement Between Owner and Contractor by and between the District and RK Roofing & Construction, Inc., San Leandro, CA, for the latter to provide demolition, installation and replacement of existing roof and roof systems, as described in the Contract Documents and in Bid Form Document 00 31 01, incorporated herein by reference as though fully set forth, for the Highland Child Development Center Roof Replacement Project, in the amount of $297,000.00, which includes a contingency allowance of $40,000.00, as the lowest responsive, responsible bidder, via the Department of Buildings and Grounds, with the work anticipated to commence on June 6, 2025, and required to be completed within sixty (60) days, with an anticipated ending of August 5, 2025.
History
- Adopted on the General Consent Report