Adds $6,846 for Tulum to relocate the staff parking lot and gate for the Cole Data Center move
Tulum Innovative Engineering will remove and relocate the staff parking lot, a rolling gate pedestal and access control systems for the Cole Data Center Move Project. The district is adding $6,845.70, raising the cap from $36,507.74 to $43,353.44, and extending the end date from July 31 to December 31, 2025 (153 more days).
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Tulum Innovative Engineering, Inc. · Oakland, CA
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- May 15, 2025 – Dec 31, 2025
- This vote
- $6,845.70
- Previous total
- $36,507.74
- New total
- $43,353.44
- Funding
- Fund 21 Building Fund Measure J
- Resource / site
9750 109- Vendor no.
004387- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-1279· agendaM.-5- Outcome
- Adopted on the General Consent Report, Jun 4, 2025
Official text
Approval by the Board of Education of Amendment No. 1, General Services Agreement by and between the District and Tulum Innovative Engineering, Inc., Oakland, CA, to provide additional construction services, including the removal and relocation of the staff parking lot, rolling gate gooseneck pedestal, and access control systems, as detailed in their proposal dated April 24, 2025 attached to this amendment as Exhibit A, for the Cole Data Center Move Project, in an additional amount of $6,845.70, increasing the Agreement’s total not-to-exceed amount from $36,507.74, to $43,353.44, and extending the term of the Agreement from May 15, 2025 through July 31, 2025 to December 31, 2025, an (additional 153 days). All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report