Adds $5.33M and one year to Brailsford & Dunlavey's Measure Y program management contract
This amendment adds $5,333,861 to the contract with Brailsford & Dunlavey for continued Measure Y program management services. The text says the contract limit rises from $15,088,204 to $20,421,254, and the end date moves from June 30, 2025 to June 30, 2026.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Notes on the official text
- The official text's numbers don't add up: $15,088,204 plus $5,333,861 is $20,422,065, but it states a new total of $20,421,254. The difference ($811) is small.
- Vendor / partner
- Brailsford & Dunlavey · Washington, DC
- Action
- Amendment
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Apr 15, 2021 – Jun 30, 2026
- This vote
- $5,333,861
- Previous total
- $15,088,204
- New total
- $20,421,254
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9657 918- Vendor no.
000758- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-1469· agendaM.-13- Outcome
- Adopted on the General Consent Report, Jun 25, 2025
Official text
Approval by the Board of Education of Amendment No. 2, Measure Y Program Management Services Agreement by and between the District and Brailsford & Dunlavey, Washington, DC, for the latter to continue to provide additional program management services for the Program Management Facilities Planning and Management Project, in an additional amount of $5,333,861.00, increasing the total not-to-exceed contract price from $15,088,204.00 to $20,421,254.00, and extending the term of the Agreement from April 15, 2021 through June 30, 2025 to June 30, 2026 (an additional 365 calendar days). All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report