Adds $52,435.08 for plywood decking on the Chabot Elementary roof replacement
This change order has Stronger Building Services install a layer of half-inch plywood decking over the existing roof of the Chabot Elementary main building and library, as described in preliminary change order (PCO) No. 1. The agreement price rises from $415,000.00 to $467,435.08.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Stronger Building Services · Berkeley, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- This vote
- $52,435.08
- Previous total
- $415,000
- New total
- $467,435.08
- Schools
- Chabot Elementary School
- Funding
- Fund 140 Deferred Maintenance
- Resource / site
9914 106- Vendor no.
004110- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-1729· agendaL.-7- Outcome
- Adopted on the General Consent Report, Aug 13, 2025
Official text
Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor, by and between the District and Stronger Building Services, Berkeley, CA, for the latter to install an overlay of ½” Plywood Decking to the existing roof as identified in the PCO No. 1, for the Chabot Elementary School Main Building & Library Roof Replacement Project, in the not-to-exceed amount of $52,435.08, increasing the Agreement price from $415,000.00 to $467,435.08. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report