Raises existing contract
+$15Knew total $116K

Adds $15,424 to the Skyline High cafeteria floor project for re-ordering flooring

This change order covers Better Flooring's costs for re-mobilizing, returning materials, reordering new Marmoleum flooring and a restocking fee, as outlined in preliminary change order (PCO) No. 1. The agreement limit rises from $100,349.00 to $115,773.00.

Plain-English summary written by AI from the official text. AI summary · amounts checked against official text

Action
Change order
Category
School buildings & construction
This vote
$15,424
Previous total
$100,349
New total
$115,773
Schools
Skyline High School
Funding
Fund 13 Cafeteria Special Revenue Fund
Resource / site
5310 991
Vendor no.
009590
Presented by
Deputy Chief, Facilities Planning and Management
File
25-1743 · agenda L.-10
Outcome
Adopted on the General Consent Report, Aug 13, 2025

Official text

Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Better Flooring, Inc., El Dorado Hills, CA, covering the costs with the latter for re-mobilization, return of materials, reordering New Marmoleum Selection and Restocking Fee, as outlined in PCO No. 1, for the Skyline High School Cafeteria Floor Replacement Project, in the not-to-exceed amount of $15,424.00, increasing the not to exceed amount of the Agreement from $100,349.00 to $115,773.00. All other terms and conditions of the Agreement remain in full force and effect.

History

  1. Adopted on the General Consent Report

This is an independent project created to provide transparency to the OUSD Community, and is not affiliated with Oakland Unified District. All data used to create the Consent Report Tracker is made public by Legistar, OUSD's official platform for posting legislative records. Plain-English summaries are written by AI with narrow parameters based upon the official text of the reports. Read about how all this works.