Awards Redgwick $1.97M to replace turf at Oakland High School
Redgwick Construction will install synthetic turf and do the demolition, grading and drainage work to prepare the site at Oakland High School. The price includes a $150,000 contingency, and Redgwick was the lowest responsible bidder. Work is expected from August 14 to November 12, 2025.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
Pulled from the consent vote. Adopted in its own vote at this meeting (6–0, 1 abstaining), instead of with the rest of the consent report.
· Adopted (passed). A motion was made by Director Latta, seconded by Director Thompson, that this Agreement Between Owner and Contractor by and between the District and Redgwick Construction Company, Oakland, CA, be Adopted. The motion carried by the following vote:.
- Maximus Simmons Absent
- Marianna Smith Absent
- Rachel Latta Aye
- VanCedric Williams Aye
- Mike Hutchinson Abstained
- Patrice Berry Aye
- Clifford Thompson Aye
- Valarie Bachelor Aye
- Jennifer Brouhard Aye
- Vendor / partner
- Redgwick Construction Company · Oakland, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Aug 14, 2025 – Nov 12, 2025
- This vote
- $1,967,300
- Schools
- Oakland High School
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9657 304- Vendor no.
003557- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-1748· agendaM.-18- Outcome
- Adopted, Aug 13, 2025
Official text
Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and Redgwick Construction Company, Oakland, CA, for the latter to install synthetic turf and perform site preparation, including demolition, grading, and drainage work, in support of the new turf installation at the Oakland High School Turf Replacement Project, in the amount of $1,967,300.00, which includes a contingency of $150,000.00, as the lowest responsible bidder, rejecting all other bids, if any, with the work anticipated to commence on August 14, 2025, and required to be completed within ninety (90) days, with an anticipated ending of November 12, 2025.
History
- Adopted