Hires Data Sync Communication for $74,000 to install security cameras at Emerson Elementary
The district is hiring Data Sync Communication, the lowest responsive bidder, for $74,000.00, which includes a $7,000.00 contingency. The company will install 21 new security cameras, replace 6 existing cameras, and install a new recording server at Emerson Elementary School. Work is expected to start September 29, 2025 and finish within 90 days.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Data Sync Communication, Inc. · Berkeley, CA
- Action
- Bid award
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- Sep 29, 2025 – Dec 28, 2025
- This vote
- $74,000
- Schools
- Emerson Elementary School
- Funding
- Fund 21 Building Fund Measure Y
- Resource / site
9657 115- Vendor no.
009437- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-2101· agendaP.-6- Outcome
- Adopted on the General Consent Report, Sep 24, 2025
Official text
Approval by the Board of Education of the Agreement Between Owner and Contractor by and between the District and Data Sync Communication, Inc., Berkeley, CA, for the latter to install 21 new security cameras, replace 6 existing cameras; provide 3 attic stock cameras; furnish and install a new recording server for cameras to replace existing recorder; and program all the cameras in Milestone, for the Emerson Elementary School Security Improvement Project, in the amount of $74,000.00, which includes a contingency fee of $7,000.00, as the lowest responsive bidder, with the work anticipated to commence on September 29, 2025, and required to be completed within ninety (90) days, with an anticipated ending of December 28, 2025.
History
- Adopted on the General Consent Report