Adds $3,374.65 to Bay Construction's alarm project at Martin Luther King Jr. Elementary
This change order adds an intrusion alarm motion detector in Administration Building D and Office D7 at Martin Luther King Jr. Elementary School. It raises the contract limit from $1,127,955.49 to $1,131,330.14. The contract term is unchanged and is stated as ending June 30, 2025.
Plain-English summary written by AI from the official text. AI summary · amounts checked against official text
- Vendor / partner
- Bay Construction, Inc. · Oakland, CA
- Action
- Change order
- Category Categories and sub-categories are assigned by AI from each item's official text, using a fixed set of definitions. They can be wrong. How categories work
- School buildings & construction
- Term
- May 25, 2022 – Jun 30, 2025
- This vote
- $3,374.65
- Previous total
- $1,127,955.49
- New total
- $1,131,330.14
- Schools
- Martin Luther King Jr. Elementary School
- Funding
- Fund 25 Developer Fee
- Resource / site
9021 182- Vendor no.
000642- Presented by
- Deputy Chief, Facilities Planning and Management
- File
25-2109· agendaO.-3- Outcome
- Adopted on the General Consent Report, Sep 24, 2025
Official text
Approval by the Board of Education of Change Order No. 5, Agreement Between the Owner and Contractor by and between the District and Bay Construction, Inc., Oakland, CA, for the latter to provide additional construction services, including the installation of an intrusion alarm motion detector in Administration Building D and Office D7, as outlined in PCO No. 7 for approval, as part of the Martin Luther King Jr. Elementary School Fire and Intrusion Alarm Replacement Project, in the additional amount of $3,374.65, increasing the Agreement not to exceed amount from $1,127,955.49 to $1,131,330.14, for the unchanged term of May 25, 2022 through June 30, 2025. All other terms and conditions of the Agreement remain in full force and effect.
History
- Adopted on the General Consent Report